PGE-24-240
130 MW hybrid in Jefferson, OR · In queue since January 2024 · Proposed COD October 2027
130 MW
Capacity
1
Components
Solar
2y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-23
PGE-24-240 is a proposed 130 MW hybrid solar and battery energy storage project located in Jefferson County, Oregon. The development project, consisting of 130 MW of solar generation, is in the Portland General Electric interconnection queue, with an entry date of January 29, 2024. The proposed commercial operation date is October 23, 2027.
The interconnection agreement for PGE-24-240 is currently listed as "In Progress (unknown study)". The point of interconnection is the Redmond - Round Butte 230kV line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
OR
County
Jefferson
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
—
Point of Interconnection
Redmond - Round Butte 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PGE-24-240