Maryland Offshore Wind Energy Project (MOWEP)
247.8 MW generation in Sussex, DE · In queue since August 2015 · Proposed COD December 2027
247.8 MW
Capacity
1
Components
Offshore Wind
10y 9m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
12y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 36–60 months
Proposed COD: 2027-12-31
The Maryland Offshore Wind Energy Project (MOWEP), a proposed generation project, is located in Sussex County, Delaware. The project, with a total capacity of 247.8 MW, consists of offshore wind technology. It is listed in the PJM interconnection queue as entry AB1-056, with a queue entry date of August 31, 2015. The proposed commercial operation date is December 31, 2027. The project's interconnection agreement has been executed.
The proposed project is interconnected to the grid via Delmarva Power & Light (DPL) at the Indian River 230kV I point of interconnection. The project's status is currently listed as suspended within the PJM queue.
Generated from interconnection queue and public data sources
State
DE
County
Sussex
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DPL
Entity
PJM
Service Type
—
Point of Interconnection
Indian River 230kV I
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- INDIANRI13 KV UNIT10
- POI Substation
- Indian River South Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.