Trumbull Energy Center
940 MW generation in Trumbull, OH · In queue since October 2015 · Proposed COD January 2026
940 MW
Capacity
1
Components
Gas
10y 7m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
10y 3m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2026-01-29
The Trumbull Energy Center is a proposed 940 MW natural gas generation project located in Trumbull County, Ohio. The project is in the PJM interconnection queue as entry PJM-AB1-105, with a queue entry date of October 22, 2015, and a proposed commercial operation date of January 29, 2026. The interconnection agreement (IA) for the project has been executed.
The project, which interconnects to the Highland-Hanna 345kV line, has been the subject of recent news coverage, with 10 articles appearing in the press.
Generated from interconnection queue and public data sources
State
OH
County
Trumbull
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Highland-Hanna 345kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09