Peach Bottom Units #2 & #3
44 MW generation in York, PA · In queue since January 1970 · Proposed COD December 2018
44 MW
Capacity
1
Components
Nuclear
56y 4m
In Queue
IA Executed
IA Status
COD target: 2018
Total Duration
48y 11m
Schedule
89 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 60–120 months
Proposed COD: 2018-12-31
The proposed Peach Bottom Units #2 & #3 project is a 44 MW nuclear generation project located in York County, Pennsylvania. The project is in the PJM interconnection queue as entry PJM-AB2-175, with a queue entry date of January 1, 1970. The proposed commercial operation date was December 31, 2018, and the interconnection agreement has been executed.
The project is linked to the existing Peach Bottom 500kV power plant. The listed utility is PECO, and the point of interconnection is the Peach Bottom 500kV substation.
Generated from interconnection queue and public data sources
State
PA
County
York
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PECO
Entity
PJM
Service Type
—
Point of Interconnection
Peach Bottom 500kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- PEACHBOT22 KV UNIT02
- POI Substation
- Peach Bottom North Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Peach Bottom Units #2 & #3