Edgecome Solar Energy Center
75 MW generation in Edgecombe, NC · In queue since August 2016 · Proposed COD December 2025
75 MW
Capacity
1
Components
Solar
9y 9m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
9y 4m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-12-31
The Edgecome Solar Energy Center is a proposed 75 MW solar generation project located in Edgecombe County, North Carolina. The project is being developed within the Dominion service area and has interconnection queue ID PJM-AC1-034 in the PJM Interconnection queue. Its queue entry date is August 11, 2016, and the proposed commercial operation date is December 31, 2025. The project's interconnection agreement has been executed.
The Edgecome Solar Energy Center has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
NC
County
Edgecombe
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Heartsease DP - Mayo Dunbar 115kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.