Walnut Solar I
50 MW generation in King And Queen, VA · In queue since September 2016 · Proposed COD July 2026
50 MW
Capacity
1
Components
Solar
9y 8m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
9y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-07-14
Walnut Solar I is a proposed 50 MW solar generation project located in King And Queen County, Virginia. The project, under development within the Dominion service area, is listed in the PJM interconnection queue as entry PJM-AC1-065, with a queue entry date of September 22, 2016. The proposed commercial operation date is July 14, 2026, and the project has an Interconnection Agreement (IA) executed.
The Walnut Solar I project has been the subject of recent news coverage, with 15 articles categorized as industry, regulatory, grid, deals, and development related.
Generated from interconnection queue and public data sources
State
VA
County
King And Queen
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Harmony Village-Shackleford 115kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- POI Substation
- HARMONY
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26