Cherry Solar
180 MW generation in Northampton, NC · In queue since October 2016 · Proposed COD August 2025
180 MW
Capacity
1
Components
Solar
9y 7m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
8y 10m
Schedule
8 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-08-31
Cherry Solar is a proposed 180 MW solar generation project located in Northampton County, North Carolina. The project, developed under the utility Dominion, is in the PJM interconnection queue as entry PJM-AC1-086, with a queue entry date of October 11, 2016. The proposed commercial operation date is August 31, 2025, and the project has an Interconnection Agreement (IA) executed.
The Cherry Solar development has been featured in recent news coverage.
Generated from interconnection queue and public data sources
State
NC
County
Northampton
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Thelma 230kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- THELMAEK69 KV LD_185
- POI Substation
- Thelma Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26