Cedar Creek Solar
19.8 MW generation in New Castle, DE · In queue since October 2016 · Proposed COD May 2027
19.8 MW
Capacity
1
Components
Solar
9y 7m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
10y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2027-05-30
Cedar Creek Solar is a proposed 19.8 MW solar generation project located in New Castle County, Delaware. The project is in the PJM interconnection queue as entry PJM-AC1-091, with a queue entry date of October 19, 2016. The proposed commercial operation date is May 30, 2027, and the interconnection agreement has been executed.
The project is being developed within the Delmarva Power & Light (DPL) service area. Recent news coverage indicates industry interest in the development.
Generated from interconnection queue and public data sources
State
DE
County
New Castle
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DPL
Entity
PJM
Service Type
—
Point of Interconnection
Cedar Creek 138kV I
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CEDARCRE34.5 KV CEDARSP
- POI Substation
- Cedar Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Cedar Creek Solar