Dixon Solar
70 MW generation in Jackson, OH · In queue since November 2016 · Proposed COD February 2028
70 MW
Capacity
1
Components
Solar
9y 6m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
11y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-02-28
The proposed Dixon Solar project is a 70 MW solar generation facility located in Jackson County, Ohio. The project is being developed within the PJM Interconnection region and is interconnected to the AEP utility via the Rio-Lick 138kV point of interconnection.
The project, identified as queue ID PJM-AC1-188, entered the PJM interconnection queue on November 1, 2016, and has a proposed commercial operation date of February 28, 2028. The interconnection agreement for the project has been executed.
Generated from interconnection queue and public data sources
State
OH
County
Jackson
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Rio-Lick 138kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Dixon Solar