Pitt Solar
80 MW generation in Pitt, NC · In queue since October 2016 · Proposed COD November 2026
80 MW
Capacity
1
Components
Solar
9y 7m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
10y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-11-17
Pitt Solar is a proposed 80 MW solar generation project located in Pitt County, North Carolina. The project is in the PJM interconnection queue as entry PJM-AC1-189, with a queue entry date of October 31, 2016. The proposed commercial operation date is November 17, 2026, and the interconnection agreement has been executed. Dominion is the listed utility.
The Pitt Solar project has been the subject of recent news coverage, with six articles categorized as development, industry, and regulatory matters.
Generated from interconnection queue and public data sources
State
NC
County
Pitt
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Chinquapin-Everetts 230kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26