Halifax County Solar
80 MW generation in Halifax, NC · In queue since November 2016 · Proposed COD August 2026
80 MW
Capacity
1
Components
Solar
9y 6m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
9y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-08-09
The Halifax County Solar project is a proposed 80 MW solar generation facility located in Halifax County, North Carolina. The project is in the PJM interconnection queue as entry PJM-AC1-208, with a queue entry date of November 1, 2016, and a proposed commercial operation date of August 9, 2026. The interconnecting utility is Dominion. The project has an executed Interconnection Agreement (IA).
The Halifax County Solar project has been the subject of recent news coverage, with three articles categorized as industry news and deals.
Generated from interconnection queue and public data sources
State
NC
County
Halifax
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Cox-Whitakers 115kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM