Sycamore Creek Solar
117 MW generation in Crawford, OH · In queue since December 2016 · Proposed COD December 2025
117 MW
Capacity
1
Components
Solar
9y 5m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
9 years
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-12-16
The Sycamore Creek Solar project is a proposed 117 MW solar generation facility located in Crawford County, Ohio. The project is in the PJM interconnection queue as entry PJM-AC2-015, with a queue entry date of December 29, 2016. The proposed commercial operation date is December 16, 2025, and the Interconnection Agreement (IA) has been executed. The interconnecting utility is AEP.
The Sycamore Creek Solar project has been the subject of recent news coverage, with 10 articles appearing in industry publications. News categories include industry, grid, regulatory, deals and development.
Generated from interconnection queue and public data sources
State
OH
County
Crawford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Chatfield-Howard 138kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo ask pi reports yet for this entity.
ask pi about Sycamore Creek Solar