Circleville Solar Energy
70 MW generation in Pickaway, OH · In queue since February 2017 · Proposed COD December 2027
70 MW
Capacity
1
Components
Solar
9y 3m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
10y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2027-12-31
The Circleville Solar Energy project is a proposed 70 MW solar generation facility in Pickaway County, Ohio. The project is interconnected within the PJM Interconnection queue as entry PJM-AC2-029, with a queue entry date of February 2, 2017. The proposed commercial operation date is December 31, 2027, and the project's Interconnection Agreement has been executed. The interconnecting utility is AEP.
The Circleville Solar Energy project has been the subject of recent news coverage, with 11 articles categorized as regulatory, industry, and grid-related.
Generated from interconnection queue and public data sources
State
OH
County
Pickaway
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Circleville 138kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CIRCLEVI138 KV T1
- POI Substation
- Circleville Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26