Blue Creek Wind Farm
20 MW generation in Van Wert, OH · In queue since February 2017 · Proposed COD November 2024
20 MW
Capacity
1
Components
Solar
9y 3m
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
7y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2024-11-30
The proposed Blue Creek Wind Farm is a 20 MW solar generation project located in Van Wert County, Ohio. The project is in the PJM interconnection queue as entry PJM-AC2-044, with a queue entry date of February 7, 2017, and a proposed commercial operation date of November 30, 2024. The interconnection agreement has been executed. The interconnecting utility is AEP.
The Blue Creek Wind Farm development project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
OH
County
Van Wert
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Maddox Creek 345kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- BLUECREE34.5 KV BLUEC1WF
- POI Substation
- Maddox Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26