Eaton OH Solar
20 MW generation in Preble, OH · In queue since February 2017 · Proposed COD January 2027
20 MW
Capacity
1
Components
Solar
9y 3m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
9y 11m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-01-28
The Eaton OH Solar project is a proposed 20 MW solar generation project located in Preble County, Ohio. The project is interconnected within the PJM Interconnection region and is in the Dayton utility service area. It entered the PJM queue as project AC2-068 on February 27, 2017, and has a proposed commercial operation date of January 28, 2027.
The project's interconnection agreement (IA) has been executed. The point of interconnection (POI) is the Camden-Crystal II 69kV line.
Generated from interconnection queue and public data sources
State
OH
County
Preble
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dayton
Entity
PJM
Service Type
—
Point of Interconnection
Camden-Crystal II 69kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Eaton OH Solar