Windsor PVI
85 MW generation in Isle Of Wight, VA · In queue since March 2017 · Proposed COD September 2027
85 MW
Capacity
1
Components
Solar
9y 2m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
10y 6m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-09-04
The Windsor PVI project is a proposed 85 MW solar generation project located in Isle Of Wight County, Virginia. The project, developed by Dominion, is currently active in the PJM interconnection queue as entry PJM-AC2-079, with a queue entry date of March 3, 2017. The proposed commercial operation date is September 4, 2027, and the project has an executed Interconnection Agreement (IA).
The Windsor PVI project has been featured in recent industry news. It is interconnected to the Ivor-Oak Ridge 115kV point of interconnection.
Generated from interconnection queue and public data sources
State
VA
County
Isle Of Wight
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Ivor-Oak Ridge 115kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Windsor PVI