Walnut Solar I (PJM-AC2-110) — Project Summary

Queue ID
PJM-AC2-110
Capacity
20 MW
Technology
Solar
Status
active
Location
King And Queen, VA
Region
PJM
Developer
IA Status
IA Executed

Walnut Solar I

PJM-AC2-110BetaActiveSolarPJMLBNL + Live

20 MW generation in King And Queen, VA · In queue since March 2017 · Proposed COD July 2026

20 MW

Capacity

1

Components

Solar

9y 2m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection

Total Duration

9y 4m

Construction75%
Queue EntryMar 14, 2017

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-07-14

About

Walnut Solar I is a proposed solar generation project with a total capacity of 20 MW, located in King And Queen County, Virginia. The project is being developed within the Dominion service area and has appeared in recent news coverage. It is listed in the PJM interconnection queue as entry PJM-AC2-110, with a queue entry date of March 14, 2017, and a proposed commercial operation date of July 14, 2026.

The project's interconnection agreement (IA) has been executed. The point of interconnection (POI) is the Harmony Village-Shackleford 115kV substation.

Generated from interconnection queue and public data sources

Project Details

State

VA

County

King And Queen

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

Dominion

Entity

PJM

Service Type

Point of Interconnection

Harmony Village-Shackleford 115kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
DOMINION HUB
Hub Confidence
HIGH
POI Substation
HARMONY

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Walnut Solar I