Sycamore Cross Solar (PJM-AC2-141) — Project Summary

Queue ID
PJM-AC2-141
Capacity
240 MW
Technology
Solar
Status
active
Location
Isle Of Wight, VA
Region
PJM
Developer
IA Status
IA Executed

Sycamore Cross Solar

PJM-AC2-141BetaActiveSolarPJMLBNL + Live

240 MW generation in Isle Of Wight, VA · In queue since March 2017 · Proposed COD April 2026

240 MW

Capacity

1

Components

Solar

9y 2m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection

Total Duration

9y 1m

Schedule

1 months past proposed COD

Construction75%
Queue EntryMar 30, 2017

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-04-01

About

Sycamore Cross Solar is a proposed 240 MW solar generation project located in Isle Of Wight County, Virginia. The project is in the PJM interconnection queue as entry PJM-AC2-141, with a queue entry date of March 30, 2017, and a proposed commercial operation date of April 1, 2026. The interconnection agreement (IA) for the project has been executed. The point of interconnection is the Septa 500kV substation.

The project is linked to an existing operating plant named Sycamore Cross Solar (EIA ID 68040). Dominion is listed as the utility. Sycamore Cross Solar has been mentioned in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

VA

County

Isle Of Wight

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

Dominion

Entity

PJM

Service Type

Point of Interconnection

Septa 500kV

Data Source

LBNL + Live

AgencyIsle of Wight County Board of SupervisorsSmithfield Times · 2024-09-23
RulingApprovalSmithfield Times · 2024-09-23
Market Context
Approximate
ISO / RTO
PJM
Trading Hub
DOMINION HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
CAVALRSP34.5 KV CAVALRSP

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (1)Beta

Last updated 2026-03-26

View all articles

No ask pi reports yet for this entity.

ask pi about Sycamore Cross Solar