Sycamore Cross Solar
240 MW generation in Isle Of Wight, VA · In queue since March 2017 · Proposed COD April 2026
240 MW
Capacity
1
Components
Solar
9y 2m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
9y 1m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-04-01
Sycamore Cross Solar is a proposed 240 MW solar generation project located in Isle Of Wight County, Virginia. The project is in the PJM interconnection queue as entry PJM-AC2-141, with a queue entry date of March 30, 2017, and a proposed commercial operation date of April 1, 2026. The interconnection agreement (IA) for the project has been executed. The point of interconnection is the Septa 500kV substation.
The project is linked to an existing operating plant named Sycamore Cross Solar (EIA ID 68040). Dominion is listed as the utility. Sycamore Cross Solar has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
VA
County
Isle Of Wight
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Septa 500kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CAVALRSP34.5 KV CAVALRSP
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo ask pi reports yet for this entity.
ask pi about Sycamore Cross Solar