Staley Solar
50 MW generation in Kankakee, IL · In queue since March 2017 · Proposed COD September 2027
50 MW
Capacity
1
Components
Solar
9y 2m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
10y 6m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-09-30
The Staley Solar project is a proposed 50 MW solar generation facility in Kankakee County, Illinois. The project is located within the ComEd service area and is interconnected to the PJM grid at the Davis Creek 138kV point of interconnection.
The project, identified as queue ID PJM-AC2-154, entered the PJM interconnection queue on March 29, 2017, and has a proposed commercial operation date of September 30, 2027. The project's interconnection agreement has been executed. Staley Solar has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
IL
County
Kankakee
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Davis Creek 138kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 86 DAVIS138 KV TR71
- POI Substation
- ComEd Davis Creek Substation