Raceway Solar
10 MW generation in Kent, DE · In queue since April 2017 · Proposed COD March 2025
10 MW
Capacity
1
Components
Solar
9y 1m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
7y 11m
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-03-01
Raceway Solar is a proposed 10 MW solar generation project located in Kent County, Delaware. The project is in the PJM interconnection queue as entry PJM-AC2-186, with a queue entry date of April 1, 2017. The proposed commercial operation date is March 1, 2025.
The interconnection agreement for Raceway Solar has been executed. The project is interconnected to the DPL utility grid at the Harrington 25kV point of interconnection.
Generated from interconnection queue and public data sources
State
DE
County
Kent
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DPL
Entity
PJM
Service Type
—
Point of Interconnection
Harrington 25kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- HARRTN 69 KV RACE2SP
- POI Substation
- South Harrington Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Raceway Solar