Raceway Solar
20 MW generation in Kent, DE · In queue since March 2017 · Proposed COD March 2025
20 MW
Capacity
1
Components
Solar
9y 2m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
8 years
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-03-01
The Raceway Solar project is a proposed 20 MW solar generation project located in Kent County, Delaware. The project is in the PJM interconnection queue as entry PJM-AC2-187, with a queue entry date of March 31, 2017. The proposed commercial operation date is March 1, 2025.
The project has an Interconnection Agreement (IA) that has been executed. The interconnecting utility is Delmarva Power & Light (DPL). The point of interconnection (POI) is the Harrington 69kV substation. The project is currently listed as active in the PJM queue.
Generated from interconnection queue and public data sources
State
DE
County
Kent
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DPL
Entity
PJM
Service Type
—
Point of Interconnection
Harrington 69kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- HARRTN 69 KV RACE2SP
- POI Substation
- South Harrington Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.