Sumac Solar
80 MW generation in Bertie, NC · In queue since June 2017 · Proposed COD July 2028
80 MW
Capacity
1
Components
Solar
8y 11m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
11y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-07-01
The Sumac Solar project is a proposed 80 MW solar generation facility located in Bertie County, North Carolina. The project is being developed within the Dominion service area and has appeared in recent news coverage. It is listed in the PJM interconnection queue as entry AD1-022, with a queue entry date of June 19, 2017, and a proposed commercial operation date of July 1, 2028.
The Sumac Solar project's interconnection agreement (IA) has been executed. The point of interconnection (POI) is the Cashie-Trowbridge 230 kV line.
Generated from interconnection queue and public data sources
State
NC
County
Bertie
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Cashie-Trowbridge 230 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.