Spring Grove Solar II
150 MW generation in Surry, VA · In queue since June 2017 · Proposed COD December 2025
150 MW
Capacity
1
Components
Solar
8y 11m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
8y 6m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-12-28
Spring Grove Solar II is a proposed 150 MW solar generation project located in Surry County, Virginia. The development project, under the queue ID PJM-AD1-025, is interconnected within the PJM Interconnection queue. Its queue entry date is June 28, 2017, with a proposed commercial operation date of December 28, 2025. The project's interconnection agreement has been executed.
The proposed project is linked to the existing Spring Grove Solar 2 operating plant (EIA ID 66844). Dominion is the utility associated with the project.
Generated from interconnection queue and public data sources
State
VA
County
Surry
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Hopewell-Surry 230 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 6SURRY
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Spring Grove Solar II