Macadamia Solar
300 MW generation in Washington, NC · In queue since September 2017 · Proposed COD March 2028
300 MW
Capacity
1
Components
Solar
8y 8m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
10y 6m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-03-31
The Macadamia Solar project is a proposed 300 MW solar generation facility located in Washington County, North Carolina. The project is in the PJM interconnection queue as entry PJM-AD1-074, with a queue entry date of September 1, 2017, and a proposed commercial operation date of March 31, 2028. The interconnecting utility is Dominion.
The project has an Interconnection Agreement (IA) listed as Executed. The point of interconnection (POI) is the Trowbridge 230 kV substation. The developer is not specified in the available data.
Generated from interconnection queue and public data sources
State
NC
County
Washington
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Trowbridge 230 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- POI Substation
- Trowbridge Substation