Macadamia Solar
109 MW generation in Washington, NC · In queue since August 2017 · Proposed COD March 2028
109 MW
Capacity
1
Components
Solar
8y 9m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
10y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-03-31
Macadamia Solar is a proposed 109 MW solar generation project located in Washington County, North Carolina. The project is being developed within the PJM Interconnection queue as project number PJM-AD1-076. The project entered the queue on August 31, 2017, and has a proposed commercial operation date of March 31, 2028. The point of interconnection is the Trowbridge 230 kV substation.
The project's interconnection agreement has been executed. Dominion is the utility associated with the project. The project is currently listed as active within the PJM queue. The Macadamia Solar project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NC
County
Washington
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Trowbridge 230 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- POI Substation
- Trowbridge Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Macadamia Solar