Seven Bridges Solar
80 MW generation in Mecklenburg, VA · In queue since September 2017 · Proposed COD December 2026
80 MW
Capacity
1
Components
Solar
8y 8m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
9y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2026-12-31
Seven Bridges Solar is a proposed 80 MW solar generation project located in Mecklenburg County, Virginia. The project is in the PJM interconnection queue as entry AD1-088, with a queue entry date of September 15, 2017. Dominion is the utility, and the point of interconnection is the Briery-Clover 230 kV line.
The proposed commercial operation date for Seven Bridges Solar is December 31, 2026. The project's interconnection agreement has been executed, and its current status is listed as suspended.
Generated from interconnection queue and public data sources
State
VA
County
Mecklenburg
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Briery-Clover 230 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Seven Bridges Solar