PJM-AD1-100
850 MW generation in Ford, IL · In queue since September 2017 · Proposed COD December 2028
850 MW
Capacity
1
Components
Wind
8y 8m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
11y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2028-12-31
PJM-AD1-100 is a proposed wind generation project with a total capacity of 850 MW, located in Ford County, Illinois. The project is interconnected to the ComEd utility within the PJM Interconnection queue. The queue entry date is September 22, 2017, and the proposed commercial operation date is December 31, 2028.
The project's interconnection agreement has been executed. The point of interconnection is at the Loretto-Wilton 345 kV and Braidwood-Davis Creek 345 kV lines.
Generated from interconnection queue and public data sources
State
IL
County
Ford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.