Kingwood Solar
175 MW generation in Greene, OH · In queue since September 2017 · Proposed COD September 2026
175 MW
Capacity
1
Components
Solar
8y 8m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
9 years
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-09-30
Kingwood Solar is a proposed 175 MW solar generation project located in Greene County, Ohio. The project is in the PJM interconnection queue as entry AD1-140, with a queue entry date of September 29, 2017, and a proposed commercial operation date of September 30, 2026. The interconnection agreement (IA) for the project has been executed. The point of interconnection is the Greene-Clark 138 kV line, and the utility is ATSI.
The project is linked to an existing operating plant of the same name (Kingwood Solar) with EIA plant ID 65425. The project has been the subject of recent news coverage, with eight articles categorized as industry and regulatory news.
Generated from interconnection queue and public data sources
State
OH
County
Greene
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Greene-Clark 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26