Walnut Solar I
20 MW generation in King And Queen, VA · In queue since January 2018 · Proposed COD July 2026
20 MW
Capacity
1
Components
Solar
8y 4m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
8y 6m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-07-14
The proposed Walnut Solar I project is a 20 MW solar generation facility located in King and Queen County, Virginia. The project is in the PJM interconnection queue as entry PJM-AD2-039, with a queue entry date of January 20, 2018. Dominion is the listed utility.
The proposed commercial operation date for Walnut Solar I is July 14, 2026, and the project's interconnection agreement has been executed. The point of interconnection is the Harmony Village-Shackleford 115 kV line. The project is currently listed as active in the queue.
Generated from interconnection queue and public data sources
State
VA
County
King And Queen
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Harmony Village-Shackleford 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- POI Substation
- HARMONY
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Walnut Solar I