Broomstick Solar Energy Centergy Center
210 MW generation in Christian, IL · In queue since March 2018 · Proposed COD December 2028
210 MW
Capacity
1
Components
Solar
8y 2m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
10y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2028-12-07
The Broomstick Solar Energy Centergy Center is a proposed 210 MW solar generation project located in Christian County, Illinois. The project is in the PJM interconnection queue as entry PJM-AD2-100, with a queue entry date of March 23, 2018. The proposed commercial operation date is December 7, 2028, and the interconnection agreement has been executed.
The project is currently listed as suspended in the interconnection queue. It is to be interconnected to the ComEd utility system at the Kincaid-Pana 345 kV point of interconnection.
Generated from interconnection queue and public data sources
State
IL
County
Christian
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Kincaid-Pana 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Broomstick Solar Energy Centergy Center