Monroe-Sicklerville Road LF Solar
1.62 MW generation in Gloucester, NJ · In queue since March 2018 · Proposed COD March 2025
1.62 MW
Capacity
1
Components
Solar
8y 2m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
7 years
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-03-01
The Monroe-Sicklerville Road LF Solar project is a proposed 1.62 MW solar generation project located in Gloucester County, New Jersey. The project is in the PJM interconnection queue as entry AD2-135, with a queue entry date of March 23, 2018. The proposed commercial operation date is March 1, 2025.
The project's interconnection status is currently in the Facility Study phase. The designated point of interconnection (POI) is Williamstown 12kV. The Area Electric Cooperative (AEC) is listed as the utility. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NJ
County
Gloucester
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEC
Entity
PJM
Service Type
—
Point of Interconnection
Williamstown 12kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WILLIAMS69 KV T4
- POI Substation
- Williamstown Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.