Glen Falls Facility
45 MW generation in Harrison, WV · In queue since March 2018 · Proposed COD January 2029
45 MW
Capacity
1
Components
Gas
8y 2m
In Queue
IA Executed
IA Status
COD target: 2029
Total Duration
10y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2029-01-31
The proposed Glen Falls Facility is a 45 MW natural gas generation project located in Harrison County, West Virginia. The project is listed in the PJM interconnection queue as entry AD2-192, with a queue entry date of March 31, 2018. The proposed commercial operation date is January 31, 2029.
The project's interconnection agreement (IA) has been executed. The point of interconnection (POI) is the Glen Falls 138kV line. The queue data indicates the project is actively under development.
Generated from interconnection queue and public data sources
State
WV
County
Harrison
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Glen Falls 138kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Glen Falls Facility