Vinton Energy Storage
42 MW storage in Vinton, OH · In queue since August 2018 · Proposed COD December 2026
42 MW
Capacity
1
Components
Battery
7y 9m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
8y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 6–18 months
Proposed COD: 2026-12-31
The Vinton Energy Storage project is a proposed 42 MW battery energy storage system in Vinton County, Ohio. The project is located within the PJM Interconnection region and is being interconnected to the AEP utility grid at the Elk 138 kV point of interconnection.
The project, identified as queue ID PJM-AE1-093, entered the PJM interconnection queue on August 31, 2018, and has a proposed commercial operation date of December 31, 2026. The project's interconnection agreement has been executed, but its status is currently listed as suspended. The development project consists of 42 MW of battery storage capacity.
Generated from interconnection queue and public data sources
State
OH
County
Vinton
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Elk 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ELKGARD2138 KV T1
- POI Substation
- Elk Garden Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Vinton Energy Storage