Strinestown Solar Project
79.6 MW generation in York, PA · In queue since September 2018 · Proposed COD January 2027
79.6 MW
Capacity
1
Components
Solar
7y 8m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2027-01-07
The Strinestown Solar Project is a proposed 79.6 MW solar generation project located in York County, Pennsylvania. The project, developed under the queue ID PJM-AE1-129, is interconnected within the PJM Interconnection queue. The queue entry date is September 7, 2018, with a proposed commercial operation date of January 7, 2027. The project's interconnection agreement has been executed, but its current status is listed as suspended.
The proposed project is linked to the existing Strinestown Solar operating plant (EIA plant ID 68969). Recent news coverage indicates regulatory interest in the project.
Generated from interconnection queue and public data sources
State
PA
County
York
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ME
Entity
PJM
Service Type
—
Point of Interconnection
Zion View - Middletown 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- METED, ZIONSVIE115KV 1B12, 49498
- POI Substation
- Cly Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Strinestown Solar Project