Northern Bobwhite Solar
96 MW generation in Marion, KY · In queue since September 2018 · Proposed COD March 2027
96 MW
Capacity
1
Components
Solar
7y 8m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8y 6m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-03-15
Northern Bobwhite Solar is a proposed 96 MW solar generation project located in Marion County, Kentucky. The project, developed by an unknown entity, is interconnected to the East Kentucky Power Cooperative (EKPC) via the Marion County 161 kV point of interconnection. It entered the PJM interconnection queue on September 25, 2018, under queue ID PJM-AE1-143, and has a proposed commercial operation date of March 15, 2027. The project's interconnection agreement (IA) has been executed.
The Northern Bobwhite Solar project has been the subject of recent news coverage, with six articles appearing in categories such as deals, industry, regulatory matters, and grid infrastructure.
Generated from interconnection queue and public data sources
State
KY
County
Marion
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
Marion County 161 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.