Maroon Solar
149 MW generation in Culpeper, VA · In queue since September 2018 · Proposed COD May 2027
149 MW
Capacity
1
Components
Solar
7y 8m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8y 8m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2027-05-30
The Maroon Solar project is a proposed 149 MW solar generation facility in Culpeper County, Virginia. The project is listed in the PJM interconnection queue as entry AE1-153, with a queue entry date of September 25, 2018. The proposed commercial operation date is May 30, 2027.
The project's interconnection agreement has been executed. The Maroon Solar project is currently listed as suspended in the PJM queue. The point of interconnection is the Remington-Gordonsville 230 kV line. The interconnecting utility is Dominion.
Generated from interconnection queue and public data sources
State
VA
County
Culpeper
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Remington-Gordonsville 230 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Maroon Solar