CC Solar I
120 MW generation in Caroline, VA · In queue since September 2018 · Proposed COD June 2025
120 MW
Capacity
1
Components
Solar
7y 8m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2025-06-30
CC Solar I is a proposed 120 MW solar generation project located in Caroline County, Virginia. The project is being developed within the Dominion service area and interconnected to the PJM grid at the Ladysmith CT-St. Johns 230 kV point of interconnection. It entered the PJM interconnection queue as project AE1-157 on September 24, 2018, with a proposed commercial operation date of June 30, 2025. The interconnection agreement for the project has been executed, though the project status is currently listed as suspended.
The CC Solar I project has been the subject of recent news coverage, with eight articles appearing in the press. These articles primarily focus on regulatory matters, with additional coverage of industry trends and business deals related to the project.
Generated from interconnection queue and public data sources
State
VA
County
Caroline
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Ladysmith CT-St. Johns 230 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- LADYSMCT14 KV GT1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all 6 articlesNo ask pi reports yet for this entity.