Panther Grove Wind
350 MW generation in Woodford, IL · In queue since September 2018 · Proposed COD February 2027
350 MW
Capacity
1
Components
Wind
7y 8m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8y 5m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2027-02-01
The Panther Grove Wind project is a proposed 350 MW wind generation project located in Woodford County, Illinois. The project is interconnected within the PJM Interconnection queue as entry PJM-AE1-163, with a queue entry date of September 24, 2018, and a proposed commercial operation date of February 1, 2027. The interconnection agreement (IA) for the project has been executed.
The proposed project is linked to the existing Panther Grove Wind, LLC operating plant (EIA plant ID 63818). Recent news coverage has discussed deals related to the project, as well as its impact on the grid.
Generated from interconnection queue and public data sources
State
IL
County
Woodford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Powerton-Nevada 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- LOW