Project PJM-AE1-172 — Project Summary

Queue ID
PJM-AE1-172
Capacity
255 MW
Technology
Wind
Status
active
Location
Livingston, IL
Region
PJM
Developer
IA Status
System Impact Study

PJM-AE1-172

PJM-AE1-172BetaActiveWindPJMLBNL

255 MW generation in Livingston, IL · In queue since September 2018 · Proposed COD October 2021

255 MW

Capacity

1

Components

Wind

7y 8m

In Queue

System Impact Study

IA Status

COD target: 2021

Interconnection

Total Duration

3y 1m

Schedule

56 months past proposed COD

Impact Study25%
Queue EntrySep 25, 2018

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-10-01

About

The proposed project PJM-AE1-172 is a 255 MW wind generation project located in Livingston County, Illinois. The project is interconnected within the PJM Interconnection queue, having entered the queue on September 25, 2018. Its proposed commercial operation date is October 1, 2021. The project's interconnection status is currently in the System Impact Study phase, and the point of interconnection is the Loretto-Wilton Center.

The project, which falls within the ComEd utility territory, consists of 255 MW of wind generation capacity. It is currently listed as an active project within the PJM queue.

Generated from interconnection queue and public data sources

Project Details

State

IL

County

Livingston

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

ComEd

Entity

PJM

Service Type

Point of Interconnection

Loretto-Wilton Center

Data Source

LBNL

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
N ILLINOIS HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PJM-AE1-172