PJM-AE1-172
255 MW generation in Livingston, IL · In queue since September 2018 · Proposed COD October 2021
255 MW
Capacity
1
Components
Wind
7y 8m
In Queue
System Impact Study
IA Status
COD target: 2021
Total Duration
3y 1m
Schedule
56 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-10-01
The proposed project PJM-AE1-172 is a 255 MW wind generation project located in Livingston County, Illinois. The project is interconnected within the PJM Interconnection queue, having entered the queue on September 25, 2018. Its proposed commercial operation date is October 1, 2021. The project's interconnection status is currently in the System Impact Study phase, and the point of interconnection is the Loretto-Wilton Center.
The project, which falls within the ComEd utility territory, consists of 255 MW of wind generation capacity. It is currently listed as an active project within the PJM queue.
Generated from interconnection queue and public data sources
State
IL
County
Livingston
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Loretto-Wilton Center
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AE1-172