Jackson Center Solar Facility
20 MW generation in Mercer, PA · In queue since September 2018 · Proposed COD July 2026
20 MW
Capacity
1
Components
Solar
7y 8m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
7y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-07-31
The Jackson Center Solar Facility is a proposed 20 MW solar generation project located in Mercer County, Pennsylvania. The project is in the PJM interconnection queue as entry PJM-AE1-183, with a queue entry date of September 26, 2018, and a proposed commercial operation date of July 31, 2026. The interconnecting utility is ATSI.
The project's interconnection agreement has been executed.
Generated from interconnection queue and public data sources
State
PA
County
Mercer
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Maysville-McDowell 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.