Golden Aster Solar Energy Center (PJM-AE1-207) — Project Summary

Queue ID
PJM-AE1-207
Capacity
160 MW
Technology
Solar
Status
suspended
Location
Grant, IN
Region
PJM
Developer
IA Status
IA Executed

Golden Aster Solar Energy Center

PJM-AE1-207BetaSuspendedSolarPJMLBNL + Live

160 MW generation in Grant, IN · In queue since September 2018 · Proposed COD May 2026

160 MW

Capacity

1

Components

Solar

7y 8m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection

Total Duration

7y 8m

Suspended75%
Queue EntrySep 27, 2018

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

Construction

Construction pending

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-05-31

About

The Golden Aster Solar Energy Center is a proposed 160 MW solar generation project located in Grant County, Indiana. The project is being developed within the PJM Interconnection queue under queue ID PJM-AE1-207. Its queue entry date is September 27, 2018, and the proposed commercial operation date is May 31, 2026. The designated point of interconnection is Mississinewa-Gaston 138 kV.

The project's interconnection agreement has been executed. The transmission utility is AEP. As of the latest data, the project's status in the interconnection queue is listed as suspended. The Golden Aster Solar Energy Center has appeared in recent news coverage regarding renewable energy projects in the region.

Generated from interconnection queue and public data sources

Project Details

State

IN

County

Grant

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

PJM

Service Type

Point of Interconnection

Mississinewa-Gaston 138 kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
AEP-DAYTON HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Golden Aster Solar Energy Center