Meadow Forge Solar Energy Center
130 MW generation in Delaware, IN · In queue since September 2018 · Proposed COD November 2026
130 MW
Capacity
1
Components
Solar
7y 8m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
8y 2m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2026-11-30
The Meadow Forge Solar Energy Center is a proposed 130 MW solar generation project located in Delaware County, Indiana. The project is in the PJM interconnection queue as entry PJM-AE1-208, with a queue entry date of September 27, 2018, and a proposed commercial operation date of November 30, 2026. The interconnection agreement (IA) has been executed.
The project, which is being developed within the AEP utility territory, has been mentioned in recent industry news.
Generated from interconnection queue and public data sources
State
IN
County
Delaware
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Delaware-Van Buren 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Meadow Forge Solar Energy Center