Headwaters Wind Farm III
100 MW generation in Randolph, IN · In queue since September 2018 · Proposed COD May 2026
100 MW
Capacity
1
Components
Wind
7y 8m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
7y 8m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 18–36 months
Proposed COD: 2026-05-31
The Headwaters Wind Farm III is a proposed 100 MW wind energy project located in Randolph County, Indiana. The project, developed by AEP, is interconnected within the PJM Interconnection queue under queue ID PJM-AE1-210. The project entered the queue on September 27, 2018, and has a proposed commercial operation date of May 31, 2026. The interconnection agreement (IA) for the project has been executed.
The proposed project is currently listed as "suspended" within the PJM queue. It is slated to connect to the Desoto 345 kV point of interconnection. The Headwaters Wind Farm III project has appeared in recent news coverage regarding renewable energy development in the region.
Generated from interconnection queue and public data sources
State
IN
County
Randolph
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Desoto 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- Desoto Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Headwaters Wind Farm III