Warren Glen Storage
20 MW storage in Warren, NJ · In queue since September 2018 · Proposed COD December 2024
20 MW
Capacity
1
Components
Battery
7y 8m
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
6y 3m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2024-12-31
The Warren Glen Storage project is a proposed 20 MW battery storage project located in Warren County, New Jersey. The project is interconnected within the PJM Interconnection queue as project PJM-AE1-243, with an original queue entry date of September 29, 2018. The proposed commercial operation date is December 31, 2024.
The interconnection agreement for the Warren Glen Storage project has been executed. The designated point of interconnection is Warren Glen Storage 34.5 kV, and the project is within the Jersey Central Power & Light (JCPL) service area. The project has appeared in recent news coverage regarding energy storage development in the PJM region.
Generated from interconnection queue and public data sources
State
NJ
County
Warren
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
JCPL
Entity
PJM
Service Type
—
Point of Interconnection
Warren Glen Storage 34.5 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.