New Road Storage
120 MW storage in Loudoun, VA · In queue since December 2018 · Proposed COD September 2027
120 MW
Capacity
1
Components
Battery
7y 5m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-09-27
New Road Storage is a proposed 120 MW battery storage project located in Loudoun County, Virginia. The project is in the PJM interconnection queue as entry PJM-AE2-019, with a queue entry date of December 12, 2018, and a proposed commercial operation date of September 27, 2027. The interconnection agreement (IA) has been executed.
The project, which interconnects with Dominion at the New Road 230 kV point of interconnection, has been the subject of recent news coverage, with eight articles categorized as regulatory, industry, grid, and development related.
Generated from interconnection queue and public data sources
State
VA
County
Loudoun
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
New Road 230 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- NEWROAD 115 KV LDNOVEC
- POI Substation
- New Road Delivery Point
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.