Ridgeway Solar
120 MW generation in Mckean, PA · In queue since March 2019 · Proposed COD August 2026
120 MW
Capacity
1
Components
Solar
7y 2m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
7y 5m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-08-10
Ridgeway Solar is a proposed 120 MW solar generation project located in McKean County, Pennsylvania. The project is in the PJM interconnection queue as entry AE2-113, with a queue entry date of March 1, 2019. The proposed commercial operation date is August 10, 2026, and the interconnection agreement has been executed.
The project, which is being developed within the PENELEC service area, has been the subject of recent news coverage, with three articles categorized as industry and regulatory news.
Generated from interconnection queue and public data sources
State
PA
County
Mckean
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Farmers Valley-Ridgeway 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26