UN-Kylertown
20 MW generation in Westmoreland, PA · In queue since February 2019 · Proposed COD March 2027
20 MW
Capacity
1
Components
Solar
7y 3m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-03-01
The UN-Kylertown project is a proposed 20 MW solar generation project located in Westmoreland County, Pennsylvania. The project is in the PJM interconnection queue as entry AE2-131, with a queue entry date of February 28, 2019. Its proposed commercial operation date is March 1, 2027.
The project's interconnection agreement has been executed. The designated utility is PENELEC.
Generated from interconnection queue and public data sources
State
PA
County
Westmoreland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Philipsburg-Karthaus 34.5
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM