Axton Solar (PJM-AE2-140) — Project Summary

Queue ID
PJM-AE2-140
Capacity
201.1 MW
Technology
Solar
Status
suspended
Location
Henry, VA
Region
PJM
Developer
IA Status
IA Executed

Axton Solar

PJM-AE2-140BetaSuspendedSolarPJMLBNL + Live

201.1 MW generation in Henry, VA · In queue since March 2019 · Proposed COD December 2025

201.1 MW

Capacity

1

Components

Solar

7y 2m

In Queue

IA Executed

IA Status

COD target: 2025

Interconnection

Total Duration

6y 9m

Suspended75%
Queue EntryMar 11, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

Construction

Construction pending

Typical: 12–24 months

Commercial Operation

Proposed COD: 2025-12-31

About

Axton Solar is a proposed 201.1 MW solar generation project located in Henry County, Virginia. The project, developed under utility AEP, is interconnected within the PJM Interconnection queue as entry PJM-AE2-140, with a queue entry date of March 11, 2019. The proposed commercial operation date is December 31, 2025, and the Interconnection Agreement (IA) has been executed.

The proposed project is linked to the existing Axton Solar operating plant (EIA plant ID 65462). Axton Solar has been featured in recent news coverage, with 10 articles primarily focusing on regulatory matters. The project's status is currently listed as suspended.

Generated from interconnection queue and public data sources

Project Details

State

VA

County

Henry

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

PJM

Service Type

Point of Interconnection

Axton-Danville 138 kV

Data Source

LBNL + Live

ApplicantAmeresco±Henry County Enterprise · 2025-03-14
AgencyBoard of Zoning Appeals±Henry County Enterprise · 2022-02-04
RulingApproval±Henry County Enterprise · 2022-02-04
Market Context
Approximate
ISO / RTO
PJM
Trading Hub
DOMINION HUB
Hub Confidence
MEDIUM
Nearest Node (Estimated)
AXTONAEP34.5 KV AXTONSP
POI Substation
Axton Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (4)Beta

Last updated 2026-03-26

View all articles

No ask pi reports yet for this entity.

ask pi about Axton Solar