PJM-AE2-156
100 MW storage in City Of Chesapeake, VA · In queue since March 2019 · Proposed COD December 2021
100 MW
Capacity
1
Components
Battery
7y 2m
In Queue
System Impact Study
IA Status
COD target: 2021
Total Duration
2y 9m
Schedule
54 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-01
PJM-AE2-156 is a proposed 100 MW battery storage project located in the City Of Chesapeake, Virginia. The project, which is in the PJM queue, was entered into the queue on March 15, 2019, with a proposed commercial operation date of December 1, 2021. Dominion is the listed utility.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Yadkin 115 kV substation.
Generated from interconnection queue and public data sources
State
VA
County
City Of Chesapeake
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Yadkin 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- YADKIN4 230 KV SR_1
- POI Substation
- Yadkin Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AE2-156