Rocky Ford Solar Energy Center (PJM-AE2-166) — Project Summary

Queue ID
PJM-AE2-166
Capacity
90 MW
Technology
Solar
Status
suspended
Location
Henry, VA
Region
PJM
Developer
IA Status
IA Executed

Rocky Ford Solar Energy Center

PJM-AE2-166BetaSuspendedSolarPJMLBNL + Live

90 MW generation in Henry, VA · In queue since March 2019 · Proposed COD December 2026

90 MW

Capacity

1

Components

Solar

7y 2m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection

Total Duration

7y 9m

Suspended75%
Queue EntryMar 16, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

Construction

Construction pending

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-12-31

About

The Rocky Ford Solar Energy Center is a proposed 90 MW solar generation project located in Henry County, Virginia. The project, developed by AEP, is interconnected within the PJM Interconnection queue as entry AE2-166, filed on March 16, 2019. The proposed commercial operation date is December 31, 2026, and the interconnection agreement has been executed. The point of interconnection is the Stockton 138 kV line.

The Rocky Ford Solar Energy Center development has been the subject of recent news coverage, with eight articles appearing in industry publications. The project's status is currently listed as suspended.

Generated from interconnection queue and public data sources

Project Details

State

VA

County

Henry

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

PJM

Service Type

Point of Interconnection

Stockton 138 kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
DOMINION HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
STOCKTON69 KV LOADT2
POI Substation
Stockton Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Rocky Ford Solar Energy Center